Lesson 04 / 12 · Sequence and delay

Bridge generator startup

What changes when startup takes 60 seconds instead of 30?

Run this browser lesson →

Predict before you run

Write down your prediction, then change only the input below. In the interactive lesson, compare the starting case with the challenge and export a worksheet to retain your reasoning.

The two lesson configurations
InputStarting valueChallenge value
Generator start delay30 s60 s

Reported quantity: s elapsed. The live control accepts 0–600 s.

Worked answer

A utility failure at 300 s requests a start. A 30 s delay makes the generator ready at 330 s; a 60 s delay makes it ready at 360 s. The battery bridges both in these inputs.

Reproduce the configuration

Starting case assumptions
IT demand / simulated duration1000 kW / 1800 s
Opening battery / energy capacity100 kWh / 100 kWh
Charging power limit100 kW
Charge / discharge efficiency0.95 / 0.9
Distribution efficiency0.95
Generator start delay30 s

Scheduled events

The browser lesson applies its configuration to the utility_loss preset. Open it above, run the starting case, switch to the challenge, and use “Verify against Python” to compare complete results. Use the worksheet export to keep the prediction, completed inputs and answer together.

Sources and verification

Original material by Mohammad Rezwan Khan, engine 1.0.0. Synthetic teaching cases; no facility calibration or independent external reproduction has been established. Annual PUE planning and outage continuity are different calculations. Full scope and evidence.